It is quite troublesome to replace and overhaul the bearings of the jaw crusher. According to the summary of many years of exploration, the disassembly method used is to directly remove the flywheels on both sides of the frame. The assembly methods of the bearing of the jaw crusher machine are summarized as follows:
1. When the flywheel on the jaw crusher frame is pulled out 4/5 outwards, use a crane to hang off the take-off wheel, the hook is slightly under force, and plays a safety role until the flywheel is fully pulled out. How to make the eccentric shaft and the two eccentric bearings above it out of the moving jaw cavity, we adopted the method of using crane to lift the heavy object and directly hit the eccentric shaft head. Due to the heavy weight of the eccentric shaft and the bearings on it, we use the flywheel as the impact object, the impact time is very short, the impact force is large, and the actual effect is ideal.
2. To install the eccentric shaft and the bearing on it into the moving jaw, the process is more complicated. To place the moving jaw upright, use a flywheel under it to make it a certain height away from the ground, try to make the axis of the moving jaw cavity perpendicular to the horizontal plane, and then burn firewood under it to let the flame pass through the cavity The cavity is heated for about 1.5 hours, then the eccentric shaft is lifted and falls vertically into the cavity.
3. In order to ensure the accurate installation of the bearing, the oil seal, end cover and retaining ring of the bearing are installed in advance at the shaft end of the lifting end, and then the external bearing is installed, so that the end cover and the bearing are installed in place.
4. After installing the eccentric shaft, keep the jaw stationary, and then install another flywheel. Shuguang after-sales service personnel use three more suitable double-headed bolts, one end into the three screw holes of the shaft head, and then, hang horizontally Take off the wheel, pay attention to the up and down direction of the flywheel, slowly put it down, the shaft hole passes through the three bolts, the flat key is aligned with the keyway, put the shaft end cover on the three bolts, add the backing plate, screw the nut, and down Press the flywheel and hit the flywheel hard at the same time, so that the flywheel is installed quickly.
As a supplier with nearly 30 years' manufacturing, Shuguang Heavy Machinery also produces and sells hammer crushers, impact crushers, vertical shaft crushers, cone crushers, compound crushers, Raymond mills, high pressure mills. Powder machine, vertical mill, ultra-fine grinding machine, ball mill, double-shaft shredder and other heavy equipment crusher. Feel free to contact us for more details.
Factory Address: Longjiang West Road, Shangjie District, Zhengzhou City
Contact number: +86-371-67666660 676667
Mobile phone: 0086 13523465141
After-sales Service Department: 0371-67666667